HomeBusiness

96% Of Refurbishment Foundation At RGM Airport Complete

4 years agoSun, 23 Feb 2020 10:33:34 GMT
Share on FacebookShare on TwitterShare on LinkedIn
96% Of Refurbishment Foundation At RGM Airport Complete

The contractors who are working on refurbishing RGM Airport have completed 96% of the foundation, The Sunday Mail reports.

This was revealed by CAAZ’s public relations and communications manager Mrs Annajulia Hungwe who said:

The foundation works are now on 96 percent, with the ground floor at 62 percent and concrete works on schedule.

We are facing few setbacks but we are moving as planned, and we are currently on the 30 percent mark, which is on track

The project started in 2018 and CAAZ says the rehabilitation works are on course.

Latest Tecno Pop 8 - now available in Pindula.

$94, Cash on Delivery in Harare & Bulawayo.

WhatsApp: 0783 450 793

More: The Sunday Mail 

Tags

0 Comments

Leave a Comment


Generate a Whatsapp Message

Buy Phones on Credit.

More Deals
Feedback