HomeGeneral News

Hwange Thermal Power Station Unit 7 Now 99% Complete - Soda

1 year agoMon, 13 Feb 2023 12:49:13 GMT
Share on FacebookShare on TwitterShare on LinkedIn
Hwange Thermal Power Station Unit 7 Now 99% Complete - Soda

Energy and Power Development Minister Zhemu Soda has said the expansion of the Hwange Thermal Power Station’s Unit 7 is 99 percent complete, with only the synchronisation of the whole system set to be done.

The Unit is expected to add 300MW to the national grid upon completion.

Addressing journalists in Harare, Soda said the synchronisation will be completed anytime this month. The Herald quoted Soda as saying:

Hwange Unit 7 has actually progressed with all other systems having undergone commissioning tests and they were successful.

One of the critical stages in the commissioning of a power station is the achievement of certain revolutions of the turbine and that was achieved.

HOT DEALS:
itel A70 -
(128GB, 3GB RAM) $89,
itel A70 - (256GB, 4GB RAM) $99
itel P40
(128GB, 4GB), (6000mAh) $99
itel P40
(64GB, 4G), (6000mAh) $93
Cash on Delivery in Harare & Bulawayo. Tinotumira kwamuri inosvika.

WhatsApp: 0783 450 793

We are only left with the synchronisation of the whole system starting from where the coal is burnt, steam is produced, turbines are turned and causes the generator to produce electricity which is evacuated into the grid.

We expect that anytime from now given that the whole system is 99 percent complete; we are only left with one percent which is the synchronisation of the whole system.

Work on the project started in August 2018 using an initial $199 million from China Eximbank but its completion was delayed by the outbreak of the coronavirus in late 2019.

According to the Zimbabwe Power Company (ZPC) website, on Monday, 13 February, Hwange Thermal Power Station was generating 378MW.

Tags

15 Comments

Leave a Comment


Generate a Whatsapp Message

Buy Phones on Credit.

More Deals
Feedback