USD$1.5 Billion Hwange Expansion Project Well On Course - ZESA

4 years agoMon, 29 Jul 2019 12:33:33 GMT
Share on FacebookShare on TwitterShare on LinkedIn
USD$1.5 Billion Hwange Expansion Project Well On Course - ZESA

The Zimbabwe Power Company (ZPC), says that the USD$1.5 billion Hwange Expansion project – Unit 7 and 8 is going according to schedule and will add 600MW to the national grid upon completion in 2022. The statement reads:

The USD$1.5 billion Hwange Expansion project – Unit 7 and 8, commenced on 1 August 2018. To date, the project is at 18% to completion and on schedule.

Come January 2022 Hwange Expansion will deliver 600MW to the national electricity grid. In progress are the site levelling works for the power plant, excavations sections for unit 8 boiler house section, concrete construction of unit 8 main power building foundation, rerouting of ash pipes and Cooling Tower Water Forebay foundation.

Meanwhile, concrete construction of foundation for main power building, unit 8 section, batching plant and the construction of the chimney foundation are now complete.

Latest Tecno Pop 8 - now available in Pindula.

$94, Cash on Delivery in Harare & Bulawayo.

WhatsApp: 0783 450 793

Tags

0 Comments

Leave a Comment


Generate a Whatsapp Message

Buy Phones on Credit.

More Deals
Feedback