ZESA Paid US$4.9 Million For Transfomers, Still To Be Delivered 9 Years On

NewZWire reports that the Zimbabwe Electricity Supply Authority (ZESA) paid US$4.9 million 9 years ago to a firm for transformers which have not been delivered to date. The report reads:

ZESA 9 years ago paid US$4.9m to a firm called Pito Investments for transformers. They were never delivered.

The Zimbabwe Power Company also paid $560K to the same firm, and again no equipment was delivered. This is according to the latest report by Auditor-General Mildred Chiri.


Quick NetOne, Telecel, Africom, And Econet Airtime Recharge

If anything goes wrong, click here to enter your query.

Mildred Chiri

Mildred Chiri is Zimbabwe's Auditor General. Read More About Mildred Chiri