It’s Normal To Disregard Tender Procedures On Instructions From Minister: ZPC Boss Testifies

Zimbabwe Power Company managing director, Noah Gwariro has told the court that it is normal for the parastatal to disregard tender procedures if it receives instructions from a minister. Testifying in the case of former Energy minister Samuel Undenge who is facing charges of criminal abuse of office, Gwariro said,

I don’t see any problem with the letter of instructions from the honourable minister Undenge as we are used to working with instruction from the policyholders. We have the example of Essar Company at Ziscosteel. We did not observe tender procedures, but it came as an instruction. We also gave Essar Company a contract to work at Munyati Power Station without a tender, but it was an instruction from the minister.

Undenge is alleged to have ordered the power company to enlist the services of Fruitful Communications for its public relations despite the fact that it has its own public relations department.

The trial is still ongoing.

More: NewsDay


Quick NetOne, Telecel, Africom, And Econet Airtime Recharge

If anything goes wrong, click here to enter your query.

Munyati Power StationSamuel UndengeZimbabwe Power Company

Munyati Thermal Power Station is a coal fired, five unit, power plant about 18km north of Kwekwe. It’s design capacity is 120MW, but generally produced 100MW. In 2019, it produced about 17MW. It was started in 1946, and the current stagers were constructed from 1953... Read More About Munyati Power Station

Samuel Undenge is a Zimbabwean politician and a former member of the- Zanu- PF. He is the former Minister of Energy and Power Development.He is a Member of Parliament for Chimanimani East constituency in Manicaland province.In January of 2018 Undenge was arrested by the Zimbabwe... Read More About Samuel Undenge

The Zimbabwe Power Company (ZPC) was formed in October 1996, as part of the 2001 restructuring of Zimbabwe Electricity Supply Authority Holdings, (ZESA) under the Ministry and Energy and Power Development. The Electricity Act (Chapter 13:19) refers. Under the structure, all power generation assets and... Read More About Zimbabwe Power Company